17 June, 2010

PMP® Formula Pocket Guide

Earned Value
CV = EV - AC CPI = EV / AC
SV = EV - PV
SPI = EV / PV
EAC 'no variances' = BAC / CPI
EAC 'fundamentally flawed' = AC + ETC EAC 'atypical' = AC + BAC - EV
EAC 'typical' = AC + ((BAC - EV) / CPI) ETC = EAC - AC
ETC 'atypical' = BAC - EV
ETC 'typical' = (BAC - EV) / CPI ETC 'flawed' = new estimate
Percent Complete = EV / BAC * 100
VAC = BAC - EAC
EV = % complete * BAC

PERT
PERT 3-point = (Pessimistic+(4*Most Likely)+Optimistic)/6
PERT σ = (Pessimistic - Optimistic) / 6
PERT Activity Variance = ((Pessimistic - Optimistic) / 6)^2
PERT Variance all activities = √sum((Pessimistic - Optimistic) / 6)^2

Network Diagram
Activity Duration = EF - ES + 1 or Activity Duration = LF - LS + 1
Total Float = LS - ES or Total Float = LF – EF
Free Float = ES of Following - ES of Present - DUR of Present
EF = ES + duration - 1
ES = EF of predecessor + 1
LF = LS of successor - 1
LS = LF - duration + 1


Project Selection
PV = FV / (1+r)^n
FV = PV * (1+r)^n
NPV = Formula not required. Select biggest number. ROI = Formula not required. Select biggest number. IRR = Formula not required. Select biggest number.
Payback Period = Add up the projected cash inflow minus expenses
until you reach the initial investment. BCR = Benefit / Cost
CBR = Cost / Benefit
Opportunity Cost = The value of the project not chosen.

Communications
Communication Channels = n * (n-1) / 2

Probability
EMV = Probability * Impact in currency

Procurement
PTA = ((Ceiling Price - Target Price) / Buyer's Share Ratio) + Target
Cost

Depreciation
Straight-line Depreciation:
Depr. Expense = Asset Cost / Useful Life
Depr. Rate = 100% / Useful Life Double Declining Balance Method: Depr. Rate = 2 * (100% / Useful Life)
Depr. Expense = Depreciation Rate * Book Value at Beginning of Year Book Value = Book Value at beginning of year - Depreciation Expense Sum-of-Years' Digits Method:
Sum of digits = Useful Life + (Useful Life - 1) + (Useful Life - 2) + etc. Depr. rate = fraction of years left and sum of the digits (i.e. 4/15th)
Mathematical Basics
Average (Mean) = Sum of all members divided by the number of items. Median = Arrange values from lowest value to highest. Pick the middle
one. If there is an even number of values, calculate the mean of the
two middle values.
Mode = Find the value in a data set that occurs most often.

Values
1 sigma = 68.26%
2 sigma = 95.46%
3 sigma = 99.73%
6 sigma = 99.99%
Control Limits = 3 sigma from mean
Control Specifications = Defined by customer; looser than the control limits
Order of Magnitude estimate = -25% to +75% Preliminary estimate = -15% to + 50%
Budget estimate = -10% to +25% Definitive estimate = -5% to +10% Final estimate = 0%
Float on the critical path = 0 days
Pareto Diagram = 80/20
Time a PM spends communicating = 90%
Crashing a project = Crash least expensive tasks on critical path.
JIT inventory = 0% (or very close to 0%.) Minus 100 = (100) or -100


Acronyms
AC Actual Cost
BAC Budget at Completion BCR Benefit Cost Ratio CBR Cost Benefit Ratio
CPI Cost Performance Index
CV Cost Variance
DUR Duration
EAC Estimate at Completion
EF Early Finish
EMV Expected Monetary Value
ES Early Start
ETC Estimate to Complete
EV Earned Value
FV Future Value
IRR Internal Rate of Return
LF Late Finish
LS Late Start
NPV Net Present Value
PERT Program Evaluation and Review Technique
PTA Point of Total Assumption
PV Planned Value
PV Present Value
ROI Return on Investment
SPI Schedule Performance Index
SV Schedule Variance
VAC Variance at Completion
σ Sigma / Standard Deviation
^ "To the power of" (2^3 = 2*2*2 = 8

No comments:

Post a Comment